July 5, 2011

The Marathon: Final Flashing

So this is it...the last two days of our marathon to finish the roof and get the scaffolding down. It's been a huge push - working 10-12 hour days and even with that, extending my trip by several days to get everything done. While i have loved being up on the roof (except when we re-framed the joists in the dead of an English winter) and seeing London from this unusually serene perch, I'm ready to finish and move on...

There are a lot of small things to finish before we can take the scaffolding down, but the last "big" item is to finish all the flashing around the dormer and along the edge - again, a tricky detail to span both types of roofing: traditional slates and modern membranes.

So I started up on the flat portion of the dormer by installing lengths of heavy lead - known as "code 4 lead" - to cover the edge of the flat roofing membrane that wraps up to face of the brick wall.

Where the roofing membrane meets the brick wall
Before inserting the lead, one has to cut away at one row of mortar joints, so there's a gap for the lead to go into - fortunately I had done this messy job several weeks ago, so installing the flashing here went relatively quickly. that is (of course!) except for the tricky bits, which were at the various corners towards the edge of the dormer. That proved time consuming, but I had it done in time for a late lunch.

Late morning of July 4th - the rows of lead flashing installed
This area is the trickiest - several corners and an overhang from the coping stone
It's not too clear, but the corner flashing pieces are installed
I then spent several hours working on some of the other tasks (see next post) but by the early evening I was able to start on the final flashing task, which involved installing the lead along the edge of the dormer. This flashing detail was worked out about a month or two ago when I was finishing the slates on the dormer. This is the tricky flashing detail I've mentioned several times: it has to span two very different types of roofing.

My sketchbook where I worked out the flashing details - the one in the center of this page is the final version for the edge detail of the dormer - a wooden drip edge wrapped in lead that works over the slates and the membrane.
 Because we had previously treated and painted the wood structure, I was able to start attaching the lead right away. To further enhance the durability of the detail (and because we had a lot of extra pieces), I decided to add a row of "soakers", which are folded sheets of stainless steel used to prevent water penetration at any 90 degree intersection of slates. These "soakers" helped seal the top of the wood and were then wrapped in the code 4 lead. The lead is held in place by a series of straps that are nailed into the wood, but are cleverly covered by the flashing - a great traditional detail used for hundreds of years.

This work was only completed the following day. The last tasks involved cleaning the roof for the last time, applying a protective patina coating on all the lead, and inserting a special caulk into the open joints where the lead is inserted into the brick. This caulk prevents water from going into the brickwork, and under the lead, while allowing for the naturally-occurring movement between the brick and lead without cracking.

In the early evening able to start the edge flashing - fitting the first pieces
The stainless steel "soakers" with the lead clips awaiting the final piece of lead flashing
The completed assembly - looking up
The completed assembly - looking down. Here you can see the all-important drip-edge taking shape
Morning of July 5th (final day) - preparing to flash the edge along the flat roof
Ready to install the roughly formed lead
Here you can see the stainless steel "soakers" ready for the lead
A detail view of how the clips will be covered by the final piece of lead
Flashing finished - cleaning the roof for the last time!
View of the finished roof & flashing - her you can see the detail where two roofing types come together, with the recently completed edge flashing in the distance
Final view of the upper roof - flashing completed, lead has it's patina coating, caulking done.

July 4, 2011

The Marathon: more painting

The past week has felt like a marathon; the finish line is being able to make the call to the scaffolding company to say that we're ready for them to take the scaffold down.

We've been working full-tilt – André was in fact supposed to fly back to New York today, but we're not quite where we need to be so he's postponed his trip by a day. It's important that we get the scaffolding down now - mostly because it's very expensive to keep renting it, but also because psychologically, we are really ready to move forward. And I think that at this point we owe it to our neighbours to get it down, too!

Today we finally finished something on the long to-do list for getting the scaffolding down: the rest of the exterior painting. André and I had worked together last weekend to paint the first window, and yesterday I started working on the other windows. In order to get everything done as quickly as possible, I had to do it on my own because André was working upstairs, at roof level.

The front windows before scraping and painting
Like last weekend, the work was quite involved - I had to prep the windows by scraping off as much of the old, peeling paint as possible and fill in any rotten areas with putty before painting.

A detail of the window's condition
It all went a lot faster than last weekend because these ones are in better condition (and my technique got better as I went along). But all told, on average it still took about 3 hours per window!

Meanwhile, André had been spending ages over the previous few days prepping the exterior of the dormer for painting – he had to apply an exterior conditioning treatment and then putty over all the screws. Once the putty dried, it had to be sanded  so that the dormer would have a smooth, even finish once painted..
June 25th - Applying the wood conditioner - will make the wood ready for the exterior elements

June 27th - After waiting 2 days for the treatment to dry, patching all the holes & joints with an exterior grade filler putty
June 30th - All the screw holes and joints had to be filled with putty - turned out to be a huge job
Once the dormer was ready, I primed and painted it in between working on the windows. This was a carefully planned tag-team operation, because we were supposed to wait 16-24 hours for each coat to dry - and we found ourselves running out of time! So the primer went on the dormer early Saturday evening; the first coat of paint on Sunday morning; and the second on Sunday night.

July 2nd - Starting the primer...
André touching up the primer
July 3rd - Starting the first coat of exterior paint
André insisted on three coats of paint, so I had to wait til getting home from work today to put the final coat of paint on! In the evening I also painted the balcony posts and the clips that will attach the railing to the posts (André had painted the balcony railing during the day).


It's been an absolutely exhausting three days. We've made huge progress, and it's an amazing feeling to finally be able to step back and look at something that looks finished! But there are still so many things to be done before I can make that phone call…

July 4th - The painting completed!

July 3, 2011

Eaves and Gutters

As you may have noticed, it's often the case on this project that things don't go according to plan. Usually it's because something has gone wrong, but today it was the opposite - I was offered a few hours of help by Alan, the local handyman. He showed me how to do the gutters and eaves. I had actually been planning on pouring the balcony concrete today (having completed the balcony rebar yesterday) but with Alan's offer, I did not wish to miss out on the opportunity of an extra pair of hands and the wisdom of a veteran builder. So the concrete pour was put off for a day...

June 30th - the eaves and gutters awaiting installation
We started by putting up a series of plastic eave boards which are nailed onto the actual plywood eaves - these boards are waterproof and unlike wooden eaves do not need painting every year or two. Having an extra set of hands was great because these boards were over 12ft long and very awkward to handle - almost like trying to manoeuvre a 12ft piece of linguine...

The plastic, waterproof eave boards installed over the actual plywood eave
Once the boards were on, Alan showed me how to install the gutters. Most of the work is in determining the high point, and a slope (for the water to run) that looks correct and functions properly. We then used a string line to work everything out and then a chalk line to mark the boards. It turns out that the top of the building is not level - most likely the building had settled over the years, or they had purposely angled the top of the roof. Either way it was quite tricky to figure out the correct pitch for the gutters...that also did not look wonky. Once the line was set, it was quite simple to install the gutter supports, and then clip in the gutters themselves. By the time Alan had to leave, we had fixed the gutters along the front of the building, and I had a good understanding how to the complete the rest.

End of the day...
I only managed to get back to finishing the gutters on July 3rd, which was a Sunday, so I had to be very quiet, which made the work go a little slower. Fortunately it was completed before the end of the day and was able to move onto the many other tasks for this marathon weekend.

July 3rd - turning the first corner
Setting the brackets with a string line

Gutters clipped into place


Turning the second corner (you can see the chalk line on the eave board)

The end piece with a downspout for the leader (the vertical drain pipe)

The completed eaves and gutters

Camping vs "Glamping"

It's really ironic that someone who has never been camping in her entire life--and, more importantly has no desire to do so, ever--namely, me--is now camping at home. Actually, camping on a construction site! But I'm learning that everything is relative, and as our rather unconventional living situation enters its sixth month, at least I can say that it's vastly more comfortable now than it was in the beginning.

Some of that has to do with the fact that things are gradually becoming more "set up", as Andre likes to say. For example, he used some plywood to improvise a long table in the living room space, and we got a couple of chairs--so at least now, unlike in the first month, we have somewhere to sit other than on the air mattress!

But in truth, a lot of it has to do with the simple fact that it's summer now - the weather has made a huge difference. When we first moved in (in January), it was so cold inside that before we got our new fridge up and running, we would just leave milk outside of "the Box", and it would be fine! (Inside "the Box", we were fine, since our little fan heaters warmed up the enclosed space nicely.) Now that it's May, it's possible to spend time in the living room space even though we still don't have heat--nice not to be confined to the one "room" with the fan heaters anymore! And dealing with cold water is infinitely easier when it's 18 degrees (Celsius) rather than 8!

Anyway, the old aphorism is true: one gets used to anything. That said, things may be a lot less rough than they were in Jan/Feb, but they're definitely still not easy. I'm starting to miss having a kitchen, and living out of a suitcase--literally, because there are no closets/wardrobes/places to put anything--is getting a little tiresome. It definitely makes getting ready for work every morning more of a challenge!

But at least things are moving in the right direction... we may still be camping, five months into this project, but at least I feel like we have moved from camping to "glamping"...and for those of you who haven't come across the term and are confused by the title of this post: "Glamping" is another great British neologism, referring to "glamorous" camping!

July 2, 2011

"First fixing" finished - and a transformation!

Today the plumbers came back to finish their "first fixing" - and whereas earlier in the process I hadn't seen much physical change, today we got it in spades. The first thing they did was shut off the water supply and disconnect the few remaining old pipes.
Disconnecting the water supply
Once that was done, they completely transformed the flat by moving the kitchen sink from its original location to its final location as per Andre's design. This was possible because we have kept the mock-up of the kitchen in place. I was totally speechless when I saw this - they cut a sink-sized hole in the plywood that is serving as the kitchen "counter", separated the sink from the cabinet it was built in to, plopped the sink into the hole, and connected it to the new pipes they had installed.
Cutting the hole for the sink into the kitchen "counter"
So it's just sitting there, almost free-standing, and the pipes are still exposed. With that done, they were able to re-connect the flat to the water supply, and turn the water supply back on.
The relocated sink
As if that wasn't enough - having installed the new boiler earlier in the week, today they installed the flue. More thrillingly, with the water supply completely reconfigured, they were able to rip the ancient, grotty old boiler off the wall.
Disconnecting the old boiler
For the moment, it's still sitting in the middle of the living room, but somehow it already feels like there's more space.

The only downside to all of this excitement is that it's hard to even describe how much of a mess all this work made! The "living room" is filled with dust, sawdust and bits of pipe - not to mention, of course, the old boiler and the now-empty sink cabinet. It's overwhelming just thinking about the clean-up job ahead...
The old boiler sitting on the floor - you can see where it used to be (it's the yellow area) with the hole from the old flue

July 1, 2011

Steel rebars & concrete

With the balcony formwork finished several days ago, it was finally time to install the steel reinforcing bars and pour the concrete. I've been looking forward to this for a rather unusual reason - after finishing architecture school back in 1998, I worked for a structural engineering company overseeing and inspecting high-rise concrete construction in New York City. Having spent a year and a half doing that, I was curious to apply my knowledge first-hand, because I'd never had the opportunity to do the actual hands-on work myself (the NYC unions would not have liked that)...
1998 - New York City - overseeing high-rise concrete & rebar in New York City
Anything made of concrete is always contains a combination of steel bars, know as "rebar", and concrete, all held in place by the formwork. Concrete is actually made up of cement, sand, aggregate (or small stones) and water - these can be mixed in various proportions to achieve different strengths.
June 29th - the empty formwork
After the forwork is made, the rebars are installed - they provide critical tensile strength to hardend concrete which is very strong in compression, but not in tension. The rebar adds tensile and torsional strength while preventing cracking, making the concrete extremely strong and durable. It's probably safe to say that my rebar was overkill for our needs, but it was done correctly! Besides providing strength to the concrete, the rebar also needed to help anchor the balcony railing posts in place. With the help of our Building Control officer, Ron, we developed a great detail for the post anchors which had the rebars woven in-between. When our neighbor and local handyman stopped by, he was shocked by the amount of steel and detail in the rebar - I took that as a compliment...
Adding the bottom row of rebar
When it came time to pour the concrete several days later, I have to admit I was not looking forward to mixing it - particularly after my experience making mortar for the ridge tiles. Sure enough, it was a lot of work and quite exhausting. A concrete mixer would have made the whole thing take an hour rather than a day, but for such a small area, it was probably not worth the trouble to rent it, transport it to the site, and then carry it upstairs.

I only encountered one problem, but it turned out to be a major one - I ran out of sand and cement halfway through the pour! Looking back, it was quite funny - a classic DIY mistake of not calculating quantities - I had eyeballed the bags of sand & cement and figured it would be enough. Fortunately I was able to jump into a mini-cab and quickly buy the needed materials just a few minutes before the supply shop closed...otherwise it wouldn't have been so funny...

Pouring the concrete for our little balcony in London may not have had the scale and glamor of high-rise construction in New York, but it somehow felt like coming full circle...
The first railing post installed with the anchoring system in place
Another railing post installed
The top layer of rebar installed
July 1st - Stuffing wet newspaper into the gap between the brick and the formwork - a trick of the trade learned from my neighbor
Final alignment and leveling of the railing posts before pouring concrete
Mixing the first batch of concrete
After "pouring" the first bucket of concrete
Filling up the remaining area with concrete - the dark wood on the left is intended to remain exposed and act as a window ledge and as a stop for the concrete. Because it's higher than the lip of form-work, the resulting slope will allow water to run down and away from the window, while preventing any pooling of water.
Several buckets later after flattening and shaping the concrete to the final slope
Using a wood stud to flatten and shape the wet concrete
Halfway finished, but running out of materials! Decided at this point to run down to the supply house (before they closed) to pick up several bags of sand & concrete.
Resuming work - this is where the future balcony doors will be
Pouring the last part of the balcony
The finished balcony...just don't step on it yet!